RECYCLING AND CAPESEAL ROUTE 60

RECYCLING AND CAPESEAL ROUTE 60

The works mentioned in previous bulletins (Bulletin # 98 NOTE: Capeseal on Route 60) Have come to an end and the result is really very good.

The recycling works Portland cement and the Capeseal provided as wearing course have culminated in this work quality that carried out Serviam. Aesthetic and functional completion of the section is excellent and we recommend those not familiar with the technique of Capeseal visit the section from Sugarloaf to the city of Minas.

It is for the group BITAFAL proud to have been involved in the whole process, from the dissemination of the aforementioned techniques in lectures, conferences and in our book "High Performance Surface treatments"To see it come true with the quality achieved. Thank provided Serviam confidence in our products and services in each of the construction phases of the stretch.

UNIFORMITY AND QUALITY

UNIFORMITY AND QUALITY

Asphalts new terminal opened last October (Bulletin # 98) It allows great homogeneity of asphalts basis for the manufacture of emulsions and modified asphalts.

With these investments and operational changes in plant we are achieving consistent quality of our products. The new terminal allows we to emulsify asphalt batch of some 320 tons each that are constants in quality and consistency batch after batch of emulsion.

With asphalts available in Uruguay (AC30 and 150/200) we achieved a "Blend" that meets the requirements for emulsions classified by performance for our country exceeding 61 ° C in Grade Performance testing AASHTO M320 to prevent exudates in time summer.

Since November 2018 penetrations waste our emulsions for surface treatments are between 60 and 70 dmm and softening points above 50 ° C constant and predictable. We have also improved the quality of viscosities and emulsion to standardize the process of emulsification and the size of the stocks of finished product.

Today as never before BITAFAL has full confidence in the superior quality of its emulsions over other emulsions present in the local and regional market.

After liberation of the base to emulsify BLEND, ensuring PG having a suitable batch emulsion between 30 and 90 tons are performed according to the type of emulsion. We have duplicates for each type of emulsion allowing us to quietly release the batch laboratory prior to loading tanks.

The new tanks have agitators and load filters to remove any impurity or cream that may arise.

We have also implemented a system control content and temperature of all tanks of the plant that allows us to accurately adjust stocks and forecast production and delivery.

Laboratory incorporated a dynamic shear rheometer (DSR) and a large battery of additional tests to determine the quality of emulsions, not only as specified in the tender documents and the IRAM 6698 but for new global trends.

We have a stereo microscope to see the quality of emulsification and micelle performance level.

We are moving the way for emulsions level of performance (EPG) which will be the specifications of the future.

These great efforts are BITAFAL we have a commitment to national roads and we want things done right because that is our responsibility.

VEDA IN Surface treatments

VEDA IN Surface treatments

With the imminent entry of autumn, we should take the necessary precautions in the execution of surface treatments.

The ban begins in a few days and the most suitable for our summer climate emulsions begin to generate low yields in the execution by the cold and the few hours of insolation that we are already living.

Asphalts specifications based emulsions remain unchanged throughout the year. If the manufacturer wants a change in specifications to continue the work, we do get an email with the desired specification.

We recall that in remitos load the batch number corresponding detailed, and which can enter our website to have the Quality report and to corroborate with the requested specifications.

To maintain the quality of the works must run less meters per day before releasing traffic with some specific recommendations always looking to reduce the amount of water in the system.

We invite you to know in detail the recommendations on the following link "SEVEN RECOMMENDATIONS FOR USE OF EMULSIONS IN WINTER"

surface treatments:

1) heating the emulsion to be used above 70 ° C to promote evaporation of water from the emulsion itself.

2) Do not wet aggregates and try to use the top in the collection that are drier and drained, not load the gathering at the bottom.

3) Start the task early in the morning, regardless of the prevailing temperature, for that tranche has executed the most hours of exposure to air, wind and sun.

4) Apply TMT technologiesThat favor locking of aggregates applied, achieving superior quality and finish.

5) Have properly calibrated equipment graveled and irrigation to the quality objective is sought to be achieved.

Irrigations primer:

In these autumn and winter periods irrigation primer they are affected by the high rate of humidity in the foundations.

It must be respected as well as primers with dilute MC 1, optimum moisture application for the purpose of achieving a successful work.

By the above, it is normal for a primer in summer takes less than 1 hour in winter takes more than 24 hours to get to be acceptable.

Soil stabilization:

It is best suited to perform soil stabilization with cement or lime period.

Water needs hydration are very basic and profiling work, compaction and sealing are unmatched.

Here the sealing emulsion IRRIGATION BITAFAL 65 at 1 per square meter lt should be complemented with a sealed with quarry dust good quality.

These bases have such successful results supporting several months before recommencing graveled tasks in appropriate months.

It IS NOT WHAT THEY SAY ...

It IS NOT WHAT THEY SAY ...

During February we conducted two tours of much of the country to see how surface treatments behaved during the summer.

After having traveled more than 2800 km were able to verify that the problems of exudation that both resonated in the press and in the environment, are actually a small part of what has been done in recent months across the country.

We could risk to quantify the problem areas and we do not exceed 2 or 3% of total executed.

Exudation is fully controlled and are the result of a sum of different errors, based not only attributable to asphalt emulsions. We have traveled sections executed with national emulsions, RC2 or imported emulsions, and in all cases there exudates sections. A common denominator of most of them is running during the winter without the necessary precautions.

The emulsions BITAFAL ALWAYS comply with the current specification DNV which includes a penetration range of 50 to 200 dmm and we subdivide into soft, medium and hard to adjust to the realities of each work.

Every summer we adjusted basis or hard asphalts media but from now on is the quality of asphalt base will maintain throughout the year. Only order will manufacture soft asphalt emulsions that way unless there is a variable in the appearance of exudates.

You can read some recommendations to reduce the appearance of exudates below:

To prevent exudates is essential to work in good weather conditions to ensure proper curing of the emulsion without risk of premature detachment and redo work force overdosing asphalt.

If you have to work during the closure take the precautions mentioned in note below.

Other factors are very soft exudation base surface allowing penetration of the aggregate A treatment and reducing the proportion of several necessary. The same applies to well-graded aggregates that fill the gaps for the asphalt emulsion.

The lack of a suitable dosage criteria, use the same "recipes" for all treatments running and lack of calibration of equipment are key components for the job fails.

Aggregates with high dust content are also a problem because the reduced active adhesion usually increase the dosage asphalt irrespective of subsequent consequences.

Must professionalize dosage calibration, the release of the basis for treatments and especially the aggregates used.

Treatment well executed, even with soft emulsions, may not have bleeding problems ... and many kilometers executed last winter with soft emulsions which did not have problems when they reached the heats.

We use own and third party cookies to help us optimize your visit to our website and also to improve service delivery and thus adapt to their most relevant and useful to better their experience needs. When you click OK to continue with navigation and thus confirm that you have read the information and accept the activation of cookies.

You can allow or reject use at any time can change the Configuration Options Privacy - Cookies Policy -

Privacy settings

When you visit a website, you can store or retrieve information in your browser, mainly in the form of cookies. Check your personal services cookies here.


We track anonymous user information to improve our website.
.
  • _ga
  • _gid
  • _gat

Decline all Services
Accept all Services